FPSO Schiehallion

Client: BP

Project: FPSO Schiehallion

Scope of Work: 14 tonne replacement double drum messenger winch

Date of Completion: December 2009

Project details

Initially providing consultancy services to BP for repairs on the FPSO, offering several winch solutions, ACE Winches was then contracted to design and manufacture a 14 tonne replacement double drum messenger winch, used for cross haul and recovery operations of a loading hose.

The winch was delivered within four weeks of the order being placed.

   

  • Existing FPSO winch to be replaced
  • Existing FPSO winch to be replaced
  • Testing of repacement winch for BP Schiehallion FPSO
  • Schiehallion FPSO
  • Replacement winch on ACE Test Bed Facility